skilled workers can build a wall in days; semi-skilled workers can build a wall in days; unskilled workers can build a wall in days. If a team has skilled, semi-skilled and unskilled workers, how long it will take to build the wall?
View worked solution
Answer: D
Let the total work required to build the wall be unit.
We can find the daily work rate of a single worker in each category:
- Skilled worker ():
Since skilled workers take days, the rate of skilled worker is: - Semi-skilled worker ():
Since semi-skilled workers take days, the rate of semi-skilled worker is: - Unskilled worker ():
Since unskilled workers take days, the rate of unskilled worker is:
Now, we calculate the combined daily work rate () of the new team consisting of skilled, semi-skilled, and unskilled workers:
Taking the common denominator as :
Therefore, the time required for this team to build the wall is:
Hence, the correct option is D.