Skip to content
Official PYQ · 2019

GATE EC 2019 Set 1 Q3 — General Aptitude

Explain with AI

It would take one machine 44 hours to complete a production order and another machine 22 hours to complete the same order. If both machines work simultaneously at their respective constant rates, the time taken to complete the same order is ________ hours.

Choose one option
View answer

Answer: C

Worked explanation not available yet.

Free practice · Your answers on this page are not saved.

Published
Report a correction
Keep exploringMore General Aptitude questions