P, Q, R and S are working on a project. Q can finish the task in days, working alone for hours a day. R can finish the task in days, working alone for hours per day. Q worked hours a day but took sick leave in the beginning for two days. R worked hours a day on all days. What is the ratio of work done by Q and R after days from the start of the project?
View answer
Answer: C
Worked explanation not available yet.